How the Tree House was built

This is the house Spring Rock's owner, Rod Teeter, built and lives in today. It sits on a steep, wooded hillside in Hide-A-Way Hills, Ohio, and we call it the Tree House. The rendering above was made from the original plans. The hillside turned out so steep that some of the plans had to change: a garage door on the front, for one, would have opened onto ground that drops almost straight down. So we made alterations, and the house turned out terrific. Here is how it went up, from the first trees coming down to moving in, in our own job photos.

  1. 1 April to May 2024

    Taking down the trees

    The very first thing was clearing the trees where the driveway and the house would go. A climber took the big ones down in pieces, and the logs were hauled out.

    • A tree climber roped in high in a tree, taking it down in pieces.
    • Big log sections loaded onto a trailer by a machine.
    • Felled tree trunks lying along the cleared path on the hillside.
  2. 2 May to June 2024

    The driveway

    Next the driveway was dug out, and geotextile fabric went down with a geocell on top: a honeycomb grid that holds the stone in place. A slinger truck filled it with #57 limestone, starting at the entrance and then driving right up onto the grid as it went. It carried the truck and its 20,000 pounds of gravel with no trouble. More than two years later, we've never had to add stone to it. Erosion control like this is a must for almost every driveway.

    • The driveway's geocell grid laid out over geotextile fabric on the slope, ready to be filled with limestone gravel.
    • A machine digging out the driveway into the wooded lot.
    • Geotextile fabric being rolled out on the dug-out driveway.
    • A slinger truck on the driveway, throwing limestone into the geocell grid.
    • The finished driveway, filled with limestone gravel.
  3. 3 June 2024

    Permits, the perc test and the septic

    Here's an interesting chain of events. They wouldn't do the perc test, the soil test for the septic system, until they could get to the site, and the hillside was so steep that nobody wanted to walk it. So the driveway had to go in first, and that took its own driveway permit. We couldn't get the house permit until the soil passed the perc test. And the septic system had to go in before the house, because once the house was built there would be no way to get to it.

    • New septic tanks waiting on the gravel before they go in the ground.
    • The septic tanks set down in their trench on the hillside.
  4. 4 June 2024

    Digging out for the house

    With the permits in hand and the driveway in, we could start excavating for the house, cutting a level place into the hillside.

    • An excavator digging out the house site at the foot of the hill.
    • The hillside cut back to make a level building site.
  5. 5 June 2024

    Helical piers, down and into the hill

    Once the excavation got far enough, all the helical piers went in, before a single footing was poured. That took quite a bit of coordination. Helicals hold up the deck on the front and the deck on the side of the house, and we added more under the footers and piers of the front half of the house. Others were drilled sideways into the hill. Those come through the band board of the floor system to help anchor the house to the hillside. They average 16 feet deep. A specialized unit on the excavator installs each one and measures the soil's resistance as torque while it goes in. The structural engineer was on site the whole time, calculating everything as we went. Very precise, very engineered.

    • A helical anchor being drilled sideways into the cut hillside, with the crew on ladders guiding it.
    • A machine driving a helical anchor horizontally into the hillside while the crew checks it.
    • A helical pier being driven into the ground by a machine.
    • A helical pier going in, with the next one waiting on the ground.
  6. 6 June 2024

    Now the build could start

    Once all of that was done, we could actually start the build: finish the excavation, pour the footers with steel reinforcing on top of the piers, and start the walls. From here it became a traditional build. Because of where this house sits, a tremendous amount of effort and coordination went in before we could even begin.

    • A freshly poured concrete footing with steel bars and a pipe sleeve.
  7. 7 June to August 2024

    The ICF walls go up

    Insulated concrete forms are stacked, braced and filled with concrete. The result is a solid concrete wall with foam on both sides.

    • The crew stacking insulated concrete forms on the walls.
    • A tall finished ICF wall with its window opening, against the hillside.
    • The first ICF forms set on the footing, with rebar standing up from the concrete.
    • A worker up on top of the tall ICF walls, setting the next course.
  8. 8 July 2024

    The concrete

    The pump truck reaches in over the trees to place the concrete, and the crew pours and finishes the lower floor.

    • A concrete pump truck's boom reaching up through the trees.
    • The crew spreading concrete for the floor inside the ICF walls.
    • A concrete mixer truck coming up the new limestone driveway.
    • The smooth, finished concrete floor of the lower level.
  9. 9 July 2024

    Steel beams

    Steel beams are set across the concrete walls to carry the main floor.

    • A steel beam set across the ICF walls of the lower level.
    • A crane truck lifting a steel beam into place over the ICF walls.
  10. 10 August 2024

    Floor and framing

    The floor system goes on, and the inside walls are framed.

    • The lower level with its new floor framing overhead and walls framed in.
    • The lower level with its floor framed overhead and the stairs going in.
    • Looking along the steel beam under the new floor framing.
  11. 11 September to October 2024

    Deck and roof

    The deck framing goes on the hillside side, and the metal roof goes on.

    • The deck framing going on the side of the house that faces down the hill.
    • The crew putting the metal roof on.
    • Roof rafters set across the top of the house, against the trees.
    • A boom truck lifting metal roof panels up the steep hillside.
    • Tall scaffolding up the front of the house beside the deck, showing how high it sits.
  12. 12 October 2024

    The outside finish

    The finish coat goes on over the outside of the concrete walls.

    • Two workers on a lift putting the finish coat on the outside wall.
    • A lift raising the crew up the side of the house to finish the wall.
    • The finished outside wall and dark roof edge against a blue sky.
  13. 13 November to December 2024

    Inside: plumbing, electric, HVAC and drywall

    The plumbing, electric and HVAC (heating, cooling and the ductwork) are run, then the drywall goes up.

    • Plumbing pipes and electric wiring run through the floor framing.
    • New drywall on the ceiling, with a steel beam below.
  14. 14 Finished

    Home: the Tree House

    We dubbed it the Tree House. “As a hunter, I used to be in tree stands, and I have the same view out the front of my house now,” Rod says. “The trees are maybe 30 yards from the house, and I’m 60 to 80 feet in the air above the ground. It looks like I’m standing in a tree stand, deer hunting.” In November 2026 a buck came through the woods below the kitchen window, so Rod walked down for a closer look.

    • The finished Tree House high on a wooded hillside in winter.
    • Looking out from the Tree House to the deck and the green woods.
    • The kitchen sink of the Tree House, under a window that looks out to the deck.
    • A buck in the woods, seen through the deck railing from the kitchen window.
    • The buck looking back over his shoulder, his rack clear against the trees.
    • The buck standing broadside among the trees, showing his rack.
    • The great room from Rod's chair: tall windows full of trees, the fireplace and TV wall, and the kitchen beyond.